REJOINDER TO ENGINEER’S
STANDPOINT: HCAAP the UNFINISHED PROJECTS
It took sometime to prepare this rejoinder due to
difficulty in identifying the unknown Structural Engineer who raised this self
serving technical issue. After studying the
people/individual involved in the project particularly their motive, benefit to
gain and others, a certain Mr. Amie De La Rosa Malobago, around
45 years old of Brgy Imelda, Mondragon Northern Samar, graduate of Civil
Engineering from Divine World University in Tacloban City was identified.
Early last year 2011, Mr. Malobago joined J.D. Legaspi
Construction, the contractor of Contract No. HCAAPD-C-1, Construction of Hagbay
Diversion Dam, Irrigation, Drainage Canals & Appurtenant Structures, Including Supply, Delivery & Installation
of Steel Gates. His Curriculum Vitae (CV) was submitted to the National
Irrigation Administration Project Management Office (NIA-PMO) for evaluation to
qualify as one of the Key Personnel in the Contractors’ required Organizational
Chart. Based on the qualification standards stipulated in the Contract Documents
between NIA and the Contractor (concurred by the Foreign Banking/Funding Institution,
JICA), Mr. Malobago was found to have no substantial experience
in the construction neither in design of Dam, Irrigation & Drainage Canals and other relevant structures. He did not file any reconsideration, when in fact he cannot
accept the evaluation made. This leads further to his refusal to understand that the
PMO was just doing their job. Perhaps, his first time to join a foreign assisted project like HCAAP. Due to ill-feelings, he lost fairness, objectivity and
professionalism in his technical inquest, curiosity and inquiry. He went
too far by his unauthorized; if not illegal retrieval (from dubious sources) of
an electronic file (efile) allegedly owned by a fellow Civil Engineer Danilo de
Asis. How sure are we that those marked discarded efiles he posted as screen
shots are authentic and not altered to serve his purpose?
His assessment centered on why NIA-PMO used old
standard criteria in reinforced concrete design of major structures, including
the high foot bridge going to the dam house control steel gates. He argued
theoretically, that using old not the latest criteria lead to wrong application
of right formulas and assumptions, hence, erroneous. In actual engineering practice, however, it is not erroneous to use old
time tested design criteria instead of a new one. How are we going
to treat structures designed and constructed using the old criteria, that is, prior
to the new one? Are they also erroneous? It is only erroneous when an engineer uses standards other than the accepted old/new
design criteria. But, this was not the case in this project. All the design
computations and good for construction drawing plans prepared by the PMO passed
the bank’s consultants scrutiny and submitted for review and approval by the
NIA central office. NIA engineering design is quite unique, they are not only looked
structurally but also from view points of hydrology and hydraulics. Cost
optimization techniques are also applied to determine an acceptable risk of
damage/failure in the final design to be adapted. Professionally, he can grow better
by joining NIA as design/construction engineer even only for 3 years, an opportunity to learn how irrigation projects are designed and constructed
all over the country.
The Catubig Irrigation Diversion Dam, a gravity type rubble masonry, nine (9) meters high and with 65 meters crest width was completed and inaugurated last June 5 2010, not May 2011 as he reported inaccurately. It is regarded as the biggest irrigation dam in the island of Samar, if not in Region VIII. As shown in the pictures below, Embassy of Japan's Deputy Chief of Mission Minister Motohiko Kato (fourth from the left) cut the inaugural ceremonial ribbon held in Barangay San Isidro, Las Navas, Northern Samar and assisted by JICA, NIA, Provincial, Municipal and Barangay officials.
As baptism of fire, the Dam had tested natures
wrath when series of major floods occurred from December 2010 up
to March 2011. During the four (4) month period, almost daily extreme heavy rain falls causing several floods, overflowing the Catubig River and submerging practically the whole project area as shown in the pictures below.
Over and above
any theoretical doubts, the structural stability of the Dam speaks for itself.
On October 18, 2011 during the turn over of the NIA PMO to a new
project management, the Dam was already diverting irrigation water for year round rice
farming to around 600 hectares out of 1300 hectares potential area, pending
completion of four (4) Lateral Canals of the Catubig Right Main Canal (CRMC). At that
time, the 21 Km long CRMC from Barangay San Isidro down to San Jorge (passing 7
Barangays) in the town of Las Navas was completed and water flowed in the entire canal reached.
The Dam in its Normal Operating Conditions Viewed from Up and Down streams.
CRMC Station 0+000 Viewed from Up to Down streams
CRMC Station 20+100 Viewed from Down to Up streams
The project being partially operational, had significantly improved farming activities (such as land development/preparation, using certified or good seeds, harvesting and finally grain solar drying) as shown in the pictures below, an initial departure from the old farming practices in the area.
Correspondingly the average rice yield per hectare,
increased drastically from the traditional one & one fourth (1.25) tons
harvested once a year to four (4) tons harvested twice a year. The increased in harvest undeniably also increased initially
annual farm income, meeting one of the most important project objectives, that is, to
alleviate poverty in Catubig Valley.
At present or almost ten (10) months after
the took over (October 18, 2011) of the new project management, the on going
Hagbay and Bulao Irrigation Sub Projects (to cover an additional total
irrigable area of around 1500 hectares) suffered further delays despite the support extended by the Manager and Staff of NIA Regional Office No. VIII.
Based on the PMO July 2012 report, said sub-projects were 51.1% and
54.8% behind schedule, respectively. Unfortunately, construction of the following remaining works were
left untouched and still to be started : four (4) Lateral Canals of CRMC,
Pinipisakan Bridge Flume (for the water from the Dam to cross the Catubig
River), the 22 Km long Catubig Left Main Canal (CLMC) and its nine (9) Lateral
Canals to cover another 2000 hectares irrigable area. Bad enough, substantial
loan amount still to be disbursed will be closed on January 2013, barely five
(5) months from now.
For references purposes, the personal profile of the previous
PMO technical core group are
enumerated as follows :
Reinerio E. Irinco; Project Manager; Monthly
Project Co-Terminous; BSAE with MS in Water Resources from University of the Philippines,
Diliman, Quezon City; 38 years NIA experience, including part time consulting
services. He retired recently from NIA government service for more challenges in
the private sector.
Prisco O. Boco III; Principal Engineer C; Monthly
Project Co-Terminous; BSCE with MS units earned
and top placer in CE Board; 20 years NIA experience. He returned to NIA Regional Office No VIII in Tacloban City
to join his family and lately was hired Engineering Consultant in one of the projects of NIA Consult in Quezon City.
Danilo L. De Asis; Principal Engineer C; Monthly
Project Co-Terminous; BSCE with MS units earned; Ten (10) years NIA experience. He resigned
from the NIA PMO and joined another foreign assisted irrigation project in Laos.
David Irorita; Principal Engineer C; Monthly Project Co-Terminous;
BSCE; 20 years NIA experience. He returned to his family in Mindanao and re-joined Maridagao-Malitubog Irrigation Project, another NIA
foreign assisted project.
Buenaventura S. Poso, Jr.; Supervising Engineer A;
Monthly Project Co-Terminous; BSCE and top placer in CE Board; Nine (9) years NIA experience.
He is still with the NIA PMO as Design Unit Chief and Assistant Project Engineer.
Denis C. Lozano; Senior Engineer A; Monthly
Project Co-Terminous; BSCE with MS units earned; Nine (9) years NIA experience. He is still
with NIA-PMO as Design Unit Assistant Chief.
Elmerson M. Legarse; Supervising Engineer A; Monthly
Project Co-Terminous; BSME; Nine (9) years NIA experience. He is still with NIA PMO as
Equipment Unit Chief and supervises the design and installation of dam steel
gates, among others.
The computer literate and working full time core group (were all sons of Samar, except one from Mindanao) was complemented with a number of support
technical staff from Northern Samar with employment status either as casual, contractual and Job
Order.